Notice: Function _load_textdomain_just_in_time was called incorrectly. Translation loading for the redux-framework domain was triggered too early. This is usually an indicator for some code in the plugin or theme running too early. Translations should be loaded at the init action or later. Please see Debugging in WordPress for more information. (This message was added in version 6.7.0.) in /home1/conexjo/public_html/wp-includes/functions.php on line 6131

Deprecated: Function Redux::setHelpTab is deprecated since version Redux 4.3! Use Redux::set_help_tab( $opt_name, $tab ) instead. in /home1/conexjo/public_html/wp-includes/functions.php on line 6131

Deprecated: Function Redux::setHelpSidebar is deprecated since version Redux 4.3! Use Redux::set_help_sidebar( $opt_name, $content ) instead. in /home1/conexjo/public_html/wp-includes/functions.php on line 6131

Notice: Function _load_textdomain_just_in_time was called incorrectly. Translation loading for the js_composer domain was triggered too early. This is usually an indicator for some code in the plugin or theme running too early. Translations should be loaded at the init action or later. Please see Debugging in WordPress for more information. (This message was added in version 6.7.0.) in /home1/conexjo/public_html/wp-includes/functions.php on line 6131

Notice: Function _load_textdomain_just_in_time was called incorrectly. Translation loading for the construct domain was triggered too early. This is usually an indicator for some code in the plugin or theme running too early. Translations should be loaded at the init action or later. Please see Debugging in WordPress for more information. (This message was added in version 6.7.0.) in /home1/conexjo/public_html/wp-includes/functions.php on line 6131
Wadi Essir Waste Water Treatment Plant – ConEx

Wadi Essir Waste Water Treatment Plant

Wadi Essir Waste Water Treatment Plant

The scope of the work involved in the Wadi Essir project included the execution, commissioning and maintenance of a sewerage plant capable of handling 4.000 cubic meters per day.

The project entailed the construction of 10 anaerobic/aerobic and maturation ponds (50.000 square meters each), head works and an administration building. Aeration equipment and an operational system, a chlorination system and standby generators were also supplied and installed.

This job was started in August 1993 and completed in August 1996.


Duration of Contract: 730 Calender Days

Project Value: 7.8 million USD

Year Completed:  1996

LocationAmman – Jordan