Notice: Function _load_textdomain_just_in_time was called incorrectly. Translation loading for the redux-framework domain was triggered too early. This is usually an indicator for some code in the plugin or theme running too early. Translations should be loaded at the init action or later. Please see Debugging in WordPress for more information. (This message was added in version 6.7.0.) in /home1/conexjo/public_html/wp-includes/functions.php on line 6131

Deprecated: Function Redux::setHelpTab is deprecated since version Redux 4.3! Use Redux::set_help_tab( $opt_name, $tab ) instead. in /home1/conexjo/public_html/wp-includes/functions.php on line 6131

Deprecated: Function Redux::setHelpSidebar is deprecated since version Redux 4.3! Use Redux::set_help_sidebar( $opt_name, $content ) instead. in /home1/conexjo/public_html/wp-includes/functions.php on line 6131

Notice: Function _load_textdomain_just_in_time was called incorrectly. Translation loading for the js_composer domain was triggered too early. This is usually an indicator for some code in the plugin or theme running too early. Translations should be loaded at the init action or later. Please see Debugging in WordPress for more information. (This message was added in version 6.7.0.) in /home1/conexjo/public_html/wp-includes/functions.php on line 6131

Notice: Function _load_textdomain_just_in_time was called incorrectly. Translation loading for the construct domain was triggered too early. This is usually an indicator for some code in the plugin or theme running too early. Translations should be loaded at the init action or later. Please see Debugging in WordPress for more information. (This message was added in version 6.7.0.) in /home1/conexjo/public_html/wp-includes/functions.php on line 6131
Upgrade and Expansion of the Existing Water System (C2) – ConEx

Upgrade and Expansion of the Existing Water System (C2)

Upgrade and Expansion of the Existing Water System (C2)

ConEx’s scope of work involves remodeling of the primary and secondary domestic water supply systems at Salt city (located 20 km West of Amman city).

The pipelines are being replaced by ductile iron main pipes (total length of 56 km with a diameter ranging from 4” to 16”), secondary polyethylene pipes (total length of 140 km with a diameter ranging from ¾” to 2”) and galvanized from ½” to 1”). 

The work on the project commenced in January 1995 and is scheduled to be completed by January 1997.


Duration of Contract: 730 Calender Days

Project Value: 7.9 million USD

Year Completed:  2000

Location:  Salt – Jordan